Olympias Phase II Project _Structural & Mechanical Installation (SP2 & SP3) Main Production Building & Filtering Area

About this Project

EKME carried out assembly and installation of structural steelwork, equipment , inspection and pre-commissioning for SP2 main production building area including grinding, flotation, cyclones, regrind ,reagents and SP3 Filtering Area.

Operations
Service

Structural and mechanical works in mining facilities

Year Of Completion

2017

Location

Greece (Olympias, Chalkidiki)

Client

Hellas Gold Single Member S.A.

End User

Hellas Gold Single Member S.A.